WARRIOR LODGE PROJECT
In June 2018, Sensei Holzbauer broke ground on Warrior Lodge which will be 40’x72′. When it is complete, the lodge will have a downstair dinning/meeting/training area with just a little more square footage than the dojo annex. There will also be a kitchen and shower rooms and the facility will be climate controlled so it can be used year round. The lumber used will be from three log cabin kits plus timbers he cut off of his property and the dojo property. Much of the furniture will be hand made by himself and some of our other wood working black belts.
Here are photos of the progress:
June 11th, 2018 – ground breaking
October 2nd, 2018 – piers
October 17, 2018 – Subfloor
October 22nd – Just a few logs in the corner
November 5th, 2018
November 29th, 2018
January 28th, 2019
March 12th, 2019
March 28th, 2019
March 29th, 2019 – Warrior Lodge Video
September 21st, 2019
September 19th, 2020 – fully enclosed with porch and steps
September 26th, 2020 – Interior